Corwen Development

We are now running to DWYRAIN CORWEN EAST

Up to Date News Letters can be found in the ‘News’ section of the website.

Llangollen Railway Trust

On Wednesday 22nd October 2014 the first passenger train ran into Dwyrain Corwen East.

Thus completing phase one of the Corwen Extension project.

CORWEN IN 2018

The  graphic, courtesy of Steam Railway magazine, shows the state of play on the Corwen Central site at the beginning of 2018.

The area to the left (western end) is essentially complete, the area in the middle is the current work priority for 2018 and to the right (eastern end) is the challenge for the beginning of 2019 when we aim to be able to connect with the existing railhead at Dwyrain Corwen East.

In 2018 the foundations and association pipe work for the water tower will be tackled to connect to the borehole in its newly erected Pump House. Then the footings for the platform 1 will be excavated and concreted to allow the building with Easi-blocs and other blocks to create the wall. When complete, the area of the island platform will require in-fill with approx. 10,000 tonnes of spoil to the levelled and compacted. Paving will follow and provision for platform furniture. The pipework and connections for this infrastructure are now in place.

This work will require considerable expenditure and, whilst we have Welsh Government European grant aid to the tune of £128k for the platform, that is only 80% of the cost. The in-filling of the void between the two walls is the subject of an appeal – Tenner for a Tonne – to pay for the contractor to bring in the spoil recovered from the remains of the old Ruthin branch embankment.

If all goes well, by the end of the summer season, the completion of the platform loop line will allow connection to the points for the siding and mainline.

We still have a lot to do and completion of the project is dependent upon the valiant efforts of the volunteers involved in the work, aided as needed by contractors.

Funding is the key to the successful completion of this project and any assistance you can give to speeding the work will be gratefully received, either by donation to specific aspects of the work or purchase of shares in Llangollen Railway PLC – the Big Push Appeal – of which 235,000 remain available.

With your help we will be able to steam the first train into Corwen Central early on 2019. Financial offers of support can be sent to the Corwen Railway Development Project, details of how to donate can be found in the Corwen News letters.

Our thanks to Toby Jennings at Steam Railway magazine for use of the site progress plan which we will update as work is completed.

LLANGOLLEN RAILWAY TRUST; PRESS RELEASE – 12 June 2018 – Immediate

LLANGOLLEN RAILWAY TAKES DELIVERY OF A HERITAGE WATER TANK

The latest stage in the Corwen Central Railway Development Project has seen a major item of railway infrastructure installed at the station site in the form of a traditional style of parachute water tank, as used in the steam era.

Brought round by road from the premises of Barnett Engineering Ltd in Rhosllanerchrugog, the installation took place on Tuesday, 12 June.

The cylindrical water tank sits on top of a column and is designed to hold 2,000 gallons of water for rapid delivery to replenish the tanks of a steam locomotive. Standing seven metres high, the completed facility weighs in at five tonnes. It incorporates a modern gate value delivery system and will draw water from a borehole sited next to the railway at Corwen.  The structure has been built to modern standards using fabrication and welding methods to meet current regulatory requirements, yet retains the appearance of an item of heritage equipment.

A Llangollen Railway spokesman said, “This latest addition to the railway facilities is now a major feature on the Corwen site and a further statement of our intent to complete the terminus station.

During a slick two-hour operation, the complete assembly of water tank and its supporting column was off-loaded, pulled erect and lifted on to the base of a previously prepared foundation plinth. With the access stairs and swivel water delivery arm attached, this new item of infrastructure stands at the eastern end of platform 2 and will service locomotives standing on either of the loop lines. A trial filling of water must await the construction of a sump and drain away, once the borehole water supply is connected.”

“Installation of this new item of heritage railway equipment has only been possible through the generous donations from members and supporters who have raised £17,000 in funding as a major contribution to the project to provide a water supply for locomotives at the new terminus. Work to complete the station and its facilities continues with the next stage concentrating on building the platform 1 wall during the summer. An opening of the Corwen station in 2019 remains dependent on the acquisition of resources in terms of materials, manpower and finance and continued support is necessary if we are to achieve that aim.”

Speaking for Barnett Engineering Ltd, Managing Director, Steve Barnett, said, “When we were asked to construct this steam-age item of equipment we thought it a little unusual, but the job was accepted as a challenge. However, it proved well within our capacity to design and manufacture and we are pleased to see the completed job delivered to Corwen where it will be installed at the new station site.”

George Jones Llangollen Railway Trust, The Station, Llangollen LL20 8SN

01978 860979

More information on fundraising for phase 2 to follow and more can be found on the below link –

http://www.llangollen-railway.org.uk/corext2.html

Information: Additional donation and application forms are available from Llangollen Railway, The Station, Abbey Road, Llangollen LL20 8SN Tel: 01978 860979 Email: info@llangollen-railway.co.uk. Completed forms should be returned to the same address.

Llangollen Railway Trust, The Station, Abbey Road, Llangollen LL20 8SN – Registered Charity No 1046614, Registered Company No 304033